Identified ADA Compliance Projects and Programmed Capital Projects with ADA components/improvements
2/5/2019
Name/Description | Status | ADA Component(s) |
CDBG South El Camino Real Sidewalk Infill | Completed | Construction of approximately 600’ of sidewalk south of San RafaelAlso added ADA compliant curb ramp and upgraded APS push button system at intersection corner. This project completed last remaining portion of the east side of ECR without sidewalk between downtown and Viejo Camino. |
CDBG Atascadero Mall Sidewalk Infill | Completed | Construction of approximately 500’ of ADA complaint sidewalk and two ADA curb ramps connecting the north edge of Atascadero Mall with the pedestrian undercrossing of 101. |
CDBG Traffic Wall ADA Improvements | 2017/2018 | Replace non-compliant ADA Curb Ramps, Driveway Approaches and Sidewalk |
North ECR Pavement Rehabilitation | Completed | Construction of approximately 400’ of new ADA compliant sidewalk at two locations along the west edge of El Camino Real. Addition of sidewalk completes the last remaining unimproved road edge along this side of ECR from San Jacinto Road to San Benito Road. Additional ADA improvements included the replacement of all existing non-complaint ramps between San Anselmo East and San Benito Road with new ADA-compliant ramps (9 total). |
FY 2015/2016 F-14 Pavement Rehabilitation | Construction | Replace non-compliant sidewalk and curb ramps on San Andres Road. |
Via Avenue Bridge Replacement | Design | Bridge Replacement includes new sidewalk to connect Via Ave. to Ensenada Ave. |
Zoo Garden Event Center | Design | Includes ADA compliant pedestrian pathways and reconstruction of portion of existing parking area for ADA parking spaces. |
Highway 41 Multi-Purpose Pathway | Completed | Construction of approximately ½ mile ADA compliant multi-use pathway between Portola Road and San Gabriel Road. Other ADA improvements include compliant curb ramps at NW intersection corner of San Gabriel/Hwy 41 and the SW corner of Portola Road/Highway 41, and compliant benches. |
Centennial Bridge and Plaza Project | Completed | ADA components of larger improvement project included all ADA compliant sidewalks connecting Lewis Ave to El Camino Real, and East Mall to Colony Square, addition of four ADA parking spaces within the City Hall Parking lot, ADA compliant curb ramps at intersection of East Mall with Palma Ave and Lewis Ave. |
ALPS Trailhead and Parking Lot | Construction | Construction of ADA parking facilities and pathway to adjacent ALPS Trailhead. |