El Dorado Road Maintenance Project

El Dorado Road

Project Summary

Pavement rehabilitation may include removal and roadway reconstruction, overlay, resurfacing and minor drainage improvements.

Project Location

Between Santa Fe Road and La Linia Avenue.

Project Cost & Funding Sources

  • Measure F-14 sales tax revenue.

Specifications

  • Project Status: Completed
  • Project Year: 2020-2021
  • Beginning Location: Santa Fe Road
  • Ending Location: La Lina Avenue
  • Pre-Project PCI: 60
  • Finished PCI: 71
  • Length (ft): 725
  • Width (ft): 20
  • Area (sq ft): 14,500

List of Measure F-14 Road Projects

Click on a street name to view more information.

  • Completed FY 2015-2016
    Alamo Avenue From: Rosario Ave - To: Barrenda Ave
  • Completed FY 2016-2017
    Alcantara Avenue From: Marchant Ave North - To: Marchant Ave South
  • Completed FY 2020-2021
    Alegre Avenue From: Atascadero Avenue - To: End
  • FY 2025-2026
    Andrita Road From: Casanova Ave - To: Sierra Vista Rd
  • Completed FY 2021-2022
    Ardilla Road From: Balboa Rd - To: North End
  • Completed FY 2015-2016
    Arena Road From: San Benito Rd - To: Yerba Ave
  • FY 2023-2024
    Ash Street From: Catalpa St - To: El Camino Real
  • Completed FY 2018-2019
    Balboa Road From: San Fernando Rd - To: Graves Creek Rd
  • Completed FY 2021-2022
    Balboa Road From: San Fernando Rd - To: Santa Ana Rd
  • FY 2023-2024
    Bella Vista Road From: San Marcos Rd - To: End
  • FY 2023-2024
    Birch Street From: Catalpa St - To: End
  • Bid Phase FY 2022-2023
    Cabrillo Avenue From: Ensenada Ave - To: Capistrano Ave
  • Completed FY 2017-2018
    Capistrano Avenue From: Sycamore Rd - To: West Mall
  • Bid Phase FY 2023-2024
    Capistrano Avenue From: West Mall - To: Lewis Ave
  • FY 2023-2024
    Capistrano Avenue From: Highway 41 - To: Lewis Ave
  • FY 2023-2024
    Carmelita Avenue From: San Andres Ave - To: Curbaril Ave
  • Completed FY 2016-2017
    Carmelita Road From: Portola Rd - To: San Gabriel Rd
  • Completed FY 2016-2017
    Carmelita Road From: Curbaril Ave - To: Portola Rd
  • FY 2024-2025
    Carmelita Road From: Portola Rd - To: Curbaril Ave
  • FY 2024-2025
    Carmelita Road From: Portola Rd - To: San Gabriel Rd
  • Completed FY 2015-2016
    Cascabel Road From: North End - To: Santa Lucia Rd
  • Completed FY 2015-2016
    Castano Avenue From: Curbaril Ave - To: Palomar Ave
  • FY 2023-2024
    Catalpa Street From: North End - To: San Rafael Ct
  • Completed FY 2021-2022
    Cebada Road From: Santa Ana Rd - To: End
  • Completed FY 2021-2022
    Cenegal Road From: Laurel Rd - To: End
  • Completed FY 2016-2017
    Colorado Avenue From: San Rafael Rd - To: San Diego Way
  • FY 2024-2025
    Colorado Avenue From: San Rafael Rd - To: San Diego Way
  • Completed FY 2020-2021
    Coromar Avenue From: Marchant Ave - To: Curbaril Ave
  • Completed FY 2020-2021
    Coromar Avenue From: Curbaril Ave - To: Portola Rd
  • Completed FY 2021-2022
    Corriente Road From: San Fernando Rd - To: Santa Ana Rd
  • Completed FY 2016-2017
    Cortez Avenue From: Maleza Ave - To: Curbaril Ave
  • FY 2023-2024
    Country Club Drive From: Capistrano Ave - To: End
  • Completed FY 2018-2019
    Del Rio Road From: Monterey Rd - To: San Gregorio Rd
  • FY 2023-2024
    Del Rio Road From: Potrero Rd - To: San Anselmo Rd
  • Bid Phase FY 2022-2023
    Dolores Avenue From: San Anselmo Ave - To: San Jacinto Ave
  • Completed FY 2020-2021
    El Dorado Road From: Santa Fe Road - To: La Lina Avenue
  • Bid Phase FY 2022-2023
    Ensenada Avenue From: Capistrano Ave - To: North End
  • Bid Phase FY 2022-2023
    Ensenada Avenue From: Via Ave - To: Capistrano Ave
  • Completed FY 2016-2017
    Estrada Avenue From: San Anselmo Rd - To: San Jacinto Ave
  • FY 2023-2024
    Flores Road From: Santa Lucia Rd - To: Los Gatos Rd
  • Completed FY 2019-2020
    Gabarda Road From: Curbaril Ave - To: Tampico Rd
  • Completed FY 2018-2019
    Garcia Road From: Santa Cruz Rd - To: San Gregorio Rd
  • FY 2025-2026
    Graves Creek Road From: Monterey Rd - To: San Fernando Rd
  • FY 2025-2026
    Graves Creek Road From: San Fernando Rd - To: Santa Ana Rd
  • Completed FY 2020-2021
    Halcon Road From: Viejo Camino - To: Calle Milano
  • FY 2023-2024
    Hermosa Avenue From: Navarette Ave - To: San Clemente Ave
  • Completed FY 2015-2016
    Honda Avenue From: Traffic Way - To: Barrenda Avenue
  • Completed FY 2019-2020
    Junipero Avenue From: El Camino Real - To: To End
  • Completed FY 2016-2017
    La Linia Avenue From: El Camino Real - To: El Dorado Rd
  • Completed FY 2016-2017
    La Linia Avenue From: West End - To: El Camino Real
  • Completed FY 2020-2021
    La Paz Lane From: Atascadero Avenue - To: End
  • FY 2024-2025
    Lake View Drive From: Portola Rd - To: Santa Rosa Rd
  • Completed FY 2020-2021
    Las Lomas Avenue From: North End - To: Principal Avenue
  • FY 2023-2024
    Las Lomas Avenue From: Principal Ave - To: El Bordo Ave
  • Completed FY 2015-2016
    Los Gatos Road From: Santa Lucia Rd - To: San Marcos Rd
  • FY 2024-2025
    Los Osos Road From: Old Morro Rd E - To: San Rafael Rd
  • Bid Phase FY 2022-2023
    Magdalena Avenue From: End - To: End
  • Bid Phase FY 2022-2023
    Magnolia Avenue From: Capistrano Ave - To: End
  • FY 2023-2024
    Maple Street From: Catalpa St - To: El Camino Real
  • Completed FY 2020-2021
    Marchant Avenue From: Curbaril Ave - To: Atascadero Ave
  • Completed FY 2020-2021
    Marchant Avenue From: Curbaril Ave - To: Coromar Ave
  • Completed FY 2020-2021
    Marchant Way From: Santa Rosa Rd - To: Pismo Ave
  • Bid Phase FY 2022-2023
    Mercedes Avenue From: Hwy 41 - To: Capistrano Ave
  • FY 2023-2024
    Monita Road From: San Gabriel Rd - To: Sierra Vista Rd
  • FY 2023-2024
    Montecito Avenue From: East Front - To: Las Lomas Ave
  • FY 2025-2026
    Monterey Court From: Monterey Ct - To: End
  • Completed FY 2018-2019
    Monterey Road From: Del Rio Rd - To: Campo Rd
  • Completed FY 2016-2017
    Monterey Road From: Campo Rd - To: San Anselmo Rd
  • FY 2024-2025
    Monterey Road From: Graves Creek Rd - To: San Anselmo Ave
  • Completed FY 2020-2021
    Mountain View Drive From: Portola Road - To: Santa Rosa Road
  • Completed FY 2016-2017
    Navajoa Avenue From: Santa Ynez - To: Curbaril Ave
  • FY 2024-2025
    Navajoa Avenue From: Atascadero Ave - To: San Andres Ave
  • Completed FY 2018-2019
    Navarette Avenue From: Santa Lucia Rd - To: San Marcos Rd
  • Bid Phase FY 2022-2023
    Navidad Avenue From: El Verano Ave - To: San Jacinto Ave
  • Completed FY 2017-2018
    Nogales Avenue From: San Jacinto Ave - To: Dolores Ave
  • Completed FY 2017-2018
    Nogales Avenue From: Dolores Ave - To: San Jacinto Ave
  • Completed FY 2020-2021
    Old Morro Road East From: Hwy 41 (West) - To: Hwy 41 (East)
  • Bid Phase FY 2022-2023
    Palma Avenue From: Traffic Way - To: Rosario Ave
  • Completed FY 2019-2020
    Palomar Avenue From: El Camino Real - To: Castano Ave
  • FY 2023-2024
    Pinewood Court From: Catalpa St - To: End
  • Completed FY 2020-2021
    Pismo Avenue From: Marchant Way - To: Hwy 41
  • Completed FY 2020-2021
    Plata Lane From: West End - To: El Camino Real
  • Completed FY 2020-2021
    Pueblo Avenue From: San Luis Avenue - To: El Camino Real
  • Completed FY 2019-2020
    Pueblo Avenue From: Sombrilla Ave - To: El Camino Real
  • FY 2025-2026
    Ramage Drive From: Portola Rd - To: End
  • Completed FY 2019-2020
    Robles Avenue From: Santa Ysabel Ave - To: Sombrilla Ave
  • Completed FY 2017-2018
    Rosario Avenue From: Olmeda Ave - To: El Camino Real
  • Completed FY 2017-2018
    Rosario Avenue From: Fresno Ave - To: Olmeda Ave
  • Completed FY 2017-2018
    Rosario Avenue From: Bajada Ave - To: Fresno Ave
  • Completed FY 2017-2018
    Rosario Avenue From: Gancho Ave - To: Bajada Ave
  • Completed FY 2017-2018
    Rosario Avenue From: Alamo Ave - To: Gancho Ave
  • Completed FY 2015-2016
    San Andres Avenue From: Santa Lucia Rd - To: San Marcos Rd
  • FY 2024-2025
    San Andres Avenue From: Santa Lucia Rd - To: San Marcos Rd
  • FY 2024-2025
    San Andres Avenue From: Marchant Ave - To: Atascadero Ave
  • FY 2023-2024
    San Andres Avenue From: San Marcos Rd - To: Hwy 41
  • Bid Phase FY 2022-2023
    San Ardo Avenue From: Arena Ave - To: Dolores Ave
  • Completed FY 2017-2018
    San Benito Road From: Colima Rd - To: Traffic Way
  • Completed FY 2015-2016
    San Clemente Avenue From: Portola Rd - To: San Marcos East
  • Completed FY 2020-2021
    San Diego Road From: Atascadero Ave - To: Colorado Rd
  • Completed FY 2020-2021
    San Diego Road From: Hwy 101 On-ramp - To: Colorado Rd
  • FY 2023-2024
    San Diego Way From: El Camino Real - To: US 101 NB Off-ramp
  • FY 2024-2025
    San Dimas Road From: Toloso Rd - To: Los Osos Rd
  • Completed FY 2020-2021
    San Gabriel Road From: Atascadero Road - To: West Front Road
  • FY 2023-2024
    San Gabriel Road From: East Front Rd - To: El Camino Real
  • Completed FY 2020-2021
    San Guillermo Lane From: End - To: San Gabriel Rd
  • Completed FY 2020-2021
    San Luis Avenue From: Pueblo Avenue - To: Curbaril Avenue
  • FY 2023-2024
    San Rafael Court From: West End - To: El Camino Real
  • Completed FY 2020-2021
    San Rafael Road From: West Front Rd - To: Atascadero Ave
  • Completed FY 2020-2021
    San Rafael Road From: Los Osos Rd - To: San Gabriel Rd
  • Completed FY 2015-2016
    San Vicente Avenue From: San Jacinto Ave - To: North End
  • FY 2025-2026
    Santa Ynez Avenue From: Atascadero Ave - To: San Andres Ave
  • Completed FY 2016-2017
    Serra Avenue From: Atascadero Ave - To: San Andres Ave
  • FY 2024-2025
    Serra Avenue From: Atascadero Ave - To: San Andres Ave
  • FY 2023-2024
    Sierra Vista Road From: San Marcos Rd - To: Monita Rd
  • Completed FY 2019-2020
    Sinaloa Avenue From: Pueblo Avenue - To: Curbaril Avenue
  • Completed FY 2020-2021
    Solano Road From: El Camino Real - To: La Lina Avenue
  • Completed FY 2019-2020
    Sombrilla Avenue From: To End - To: Robles Ave
  • Completed FY 2019-2020
    Sonora Avenue From: Valle Avenue - To: Pinal Avenue
  • Completed FY 2016-2017
    Sycamore Road From: Hidalgo Ave - To: Miramon Ave
  • Bid Phase FY 2022-2023
    Sycamore Road From: Miramon Ave (south end) - To: Capistrano Ave
  • Completed FY 2017-2018
    Tunitas Avenue From: Bajada Ave - To: Traffic Way
  • Bid Phase FY 2022-2023
    Valentina Ave From: Dolores Ave - To: Alamo Ave
  • Completed FY 2019-2020
    Valle Avenue From: Escarpa Ave - To: Curbaril Ave
  • Completed FY 2015-2016
    Valle Avenue From: Curbaril Ave - To: Palomar Ave
  • Completed FY 2019-2020
    Valle Avenue From: North End - To: Escarpa Ave
  • FY 2025-2026
    Venado Avenue From: Ardilla Ave - To: Chauplin Ave
  • Bid Phase FY 2022-2023
    Via Avenue From: Traffic Way - To: Ensenada Ave
  • Completed FY 2015-2016
    Yerba Avenue From: Estrada Ave - To: Dolores Ave

Administrative Services

City Manager's Office

Community Development

Community Services

Fire & Emergency Services

Police Department

Public Works

Login Form



Sign up for email notifications, submit online requests, edit contact info.